Nicks Island Bridge
| Value: |
$140,000.00 |
| Description: |
The work involved upgrading the load capacity of a 200’ long trestle bridge. |
| Location: |
Creston, BC |
The project involved upgrading the capacity of a 10 span, 200 foot long trestle bridge located in Creston, BC. The existing Ekki wood deck was first removed and salvaged for the owner to use on future projects. The cross ties were then removed exposing the timber stringers. All undersized or deteriorating stringers were replaced and additional stingers were added to increase the bridge capacity. A new deck was then installed.
The construction was undertaken a half a bay at a time which allowed Johnston Construction to reduce the impact to the traveling public. During work hours a single lane was maintained on the bridge to allow traffic by as work was undertaken in the other lane. The work was also timed so that at the end of each day the crew would complete a section allowing the entire bridge to be reopened overnight.
The project was completed under budget and ahead of schedule.

|